December 21, 2017













The CubeOne team have completed the precast concrete panels to the stair / lift core and post-tensioned concrete slabs.

Unfortunately a few inclement weather days prevented level 3 to roof precast concrete panels to be erected into position. However the team powered ahead with completion of the suspended concrete slabs up to level 3 – just in time for the Christmas break!

Many thanks to all out subcontractors! Have a safe and happy Christmas!






Quest Pacific Epping have reached completion of the concrete structure, topping out with the final concrete pour this week just in time for the Christmas break!

Services and fit-out subcontractors are working hard & fast through the lower levels getting a head start on the big push for next year.

Thank you to all our subcontractors for their hard work this year. We wish you a safe, and happy Christmas – see you in 2018!



Maben Group are pleased to announce that we have made the AFR Fast 100 List – and for the second time! Thank you to everyone who has supported us.

Take a look at the full 2017 list here http://www.afr.com/leadership/afr-lists/fast-100/financial-review-fast-100-2017-the-full-list-20171103-gzeg47


December 14, 2017


Maben Group are pleased to announce that we have been awarded the contract for Featherbrook Stage 2.

Located 22kms from the centre of Melbourne, Stage 2 of the Featherbrook Shopping Centre will be located on the high profile corner of Boardwalk Blvd and Sneydes Road, Point Cook.

The retail development, designed by Particular Architects, will add 13 specialty shops – both retail and food – and a commercial office to the already thriving Shopping Centre. Works will begin early 2018.

Maben Group are pleased to be working closely with Central Equity and Particular Architect, and look forward to a successful project.




The installation of concrete precast panels and structural steel has transformed the Woolworths box, with service rough and roofing works beginning this week.

The casual dining mall concrete slab entry has been poured and the Stage 2 tunnel has been installed, allowing the remainder of the concrete infill slabs on the existing slab to be poured for the new specialty tenancies and mall.


December 11, 2017

















On Monday 4 December 2017, Maben Group spent the day at Melbourne Cable Park in Bangholme.

We had a heap of fun taking on the Aqua Park, before jumping on the lake and trying our hand at the cable riding.

Thank you to Shelley and the team at Melbourne Cable Park for all the fun, and thank you to Square Meal Co for our fantastic lunch.

Such a fabulous (and exhausting) day!











Gather Advanced Photography visited our Bendigo site late November and captured a few photos of the progress.

Since November, Nigel, Greg and the team have been working hard at Kennington Village Stage 2 and the project has quickly progressed further.

The team have handed over the pad site and Tenancy 8 extension areas for shop fitting

And Tenancy 8, Edwards Providore, is now trading and are very happy.

The team are now complete with internal works to the retails spaces and are working hard to close out externals.

Take a look at some of GAP Photography’s November footage featuring Greg, Site Foreman:










Gather Advanced Photography visited the Quest Pacific Epping Site late November and the site had progressed rapidly!

Our team were getting ready to pour the first slab of level 4, laying tables on level 4 pour 2, jumping screens and the service trades were beginning on ground.

Here’s a clip from site, featuring Site Foreman, Sammy.


November 29, 2017





It’s full steam ahead at Cube One Narre Warren with the concrete structure quickly progressing.

The precast core panels have been erected, making way for Caelli’s crew to commence works on the suspended post tensioned slabs.

In-ground services across the site are nearing completion and designs for the stand alone Café building are being finalised.

It is amazing what the can be achieved when the sun finally comes out!!!





Following the fitout period, KTAS opened for trading today!

The team are all extremely satisfied with the outcome and happy to deliver another successful project.

The Clyde Medical Centre services in-grounds are complete and footings are to be poured this week.

Car park sub-base is now complete & the ground floor slab is scheduled to be poured next week.