The Quest team successfully installed the precast lids for both the stair and lift core the first week back from holidays.

Prior to Australia Day the service trades were busy on levels 1 and 2, stripping of formwork was underway, level 6 structural steel work was almost complete and the setting out of walls on level 2 and framing of level 1 had begun.




The envelope of the Woolworths box and main trading area roofing works is now complete.

With a roof over head in the box, the high level services rough in, metal stud wall erection and painting works are well underway.

The casual dining mall and tenancies existing slab remedial works are complete and the team are expecting the delivery of structural steel mid this week.





All works associated with the retail pad site are complete and practical completion has been granted.

The restaurant pad site building works have been completed with hard and soft landscaping, the final clean and demobilisation from site left to go.