Works have begun on site at the new Holden Dealership at Essendon Fields.

The existing airside pavements have been pulverised allowing the civil contractor to commence preparing the subbase.

Rough in for in-ground services has also commenced with concrete footings scheduled for next week.









Maben and all subcontractors have worked very hard in the past few weeks to reach several key milestones of the project.

The second largest portion of the project – the gym tenancy – has been handed over to the fit out contractors to commence their works.

The team have constructed a new shopfront for the Reject Shop and the store is now back open for trade.

A new shopfront has been completed for Aldi which involved new structural steel, glazing and roller shutter doors. The store has been handed over to the fit out contractors.

On the Childcare level the roof has been laid and wall framing has begun. In the external areas the concrete seating and large concrete planters have been formed up and are now ready to be poured.

Great progress team – well done!


October 22, 2018


An article from The Design Files Daily featuring Clare Cousins Architecture and our shared office space

https://thedesignfiles.net/2018/10/workspace-melbourne-architect-clarecousins/



A sneak peak at the Coles Surrey Hills project.

Well done and thank you to everyone who has been involved with this project.

Opening day is fast approaching – more photos to come!

Photo by Neoscape.

http://www.neoscape.com.au/


October 19, 2018

Maben Group are pleased to announce that Paul Pettenuzzo has joined our team as Estimating Manager.

Paul has over 25 years estimating experience and during that time has been involved in securing a wide range of projects in a range of different sectors. Paul’s wealth of experience is a great asset to our team.

Welcome aboard Paul!


October 17, 2018

Maben Group welcomed John Santalucia in the role of Project Surveyor earlier this year.

John is a highly experienced Project Surveyor with over 28 years in the Melbourne construction industry.

We are very pleased to have you on board, John.











Footing works to all buildings are now complete.

Panel installation to Buildings A1 & A2 are finished with the erection of steel continuing.

The team have completed the ground slabs to three buildings and are nearing the halfway point on the fourth.

Great progress!