Concrete pours, precast installation, steel erection – it’s been a busy few weeks at Craigieburn Junction Retail.

The last concrete pour to Building A2 is now complete, closing out all remaining suspended slab pours.

And the final precast element was installed last week.

Total element count reaching 516! Well done team.

Click on this link for a 360 view of the project in its entirety!!

https://viewer.hangar.com/360?productId=Nr7N22Kj









Maben and all the subcontractors are continuing their momentum on-site and working hard in the lead up to the end of the year.

The Pacific Epping new mall entry has been constructed with the ground slab poured, precast erected, first floor slab poured and structural steel erected all in the past few weeks.

The fa├žade cladding is well underway around the new gym tenancy on the ground level.

On level 1, the new childcare tenancy is progressing well with aluminium window and doors frames installed and plaster currently going up on walls. The external concrete planters have been poured for the childcare outdoor area.

Aldi is complete and back open for trade.







Following the pulverisation of the asphalt, the subgrade has been stripped back to the capping layer and re-compacted prior to having 1900 cubic metres brought into site to build up to the correct levels ready for footings.

Footings, including the internal inground services are now complete.







The Hillsong Church project at Knoxfield is now approaching completion.

Most trades have completed their works and commissioning of services has commenced. Externally signage is being installed, landscaping has been completed and car parks are ready to use.

Internally touch up painting is underway with fit off of most trades well over 95% complete.

Joinery is being loaded in and bench tops installed.

Carpet and vinyl flooring is well advanced with only sealed concrete floors as a finishing touch.







Craigieburn Junction is on its way up!

Building D Level 1 Slab is now complete, and scaffold & formwork to pour 1 on level 2 nearing completion.

Building A2 Level 1 Pour 1 is finished with pour 2 now ready to go.

Ground floor precast panels have been installed to all buildings.

And roofing is complete to Buildings A1 & A2 Stage 1.