Works are progressing quickly at 7 Ormond. Outside, the roof and fa├žade glazing installations are complete, with the carpark, kerbs and landscaping to commence in coming weeks.

Internally plasterboard walls are being prepared for the first coat of paint and all service-rough ins are nearing completion.







Level 5 pour began on Monday with the team standing panels on level 5 tomorrow.

Set out and framing is underway on B1, block work to B1 and ground floor continues and high level services are starting on B1 to level 1.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=MjBkNxBr

Photos by Gather Advanced Photography.










With only 1 month to go at Holden Essendon Fields, the job is starting to take shape. The Holden pylon has been installed, the workshop slab preparation is complete and the first coat of epoxy has been applied.

Internally the Showroom overhead services are complete allowing the tiling to flow through the selling floor, whilst the back of house joinery is being installed.

Externally the signage and remainder of the cladding is due to arrive next week and asphalt will be laid early June!



Structural steel is almost complete, the roof is on and capping and flashing works are up next.

Alucobond cladding also is progressing well.

The staff amenities works have begun upstairs and the Porsche Brighton team will relocate their lunch room and office shortly in order for demolition to begin.

Terrific progress team!