What a busy month it’s been for the Porsche & Volkswagen Team at Essendon Fields!

Following the completion of Porsche and associated external works, the focus has been on Volkswagen with linings, painting, joinery, doors, cladding and windows all complete.

With high level works now complete, the floor finishes are underway and the project is on track to be completed by Christmas!

Well done team.









Congratulations to the Highpoint team who have completed the new floor finishes throughout the 14,000m2 site!

It’s been a busy month for the team who also completed the Zone 1 awning. The final feature ceilings to Level 2 and North West Food Court Balustrade are due to be complete in the coming weeks.


December 2, 2020










Maben Group is pleased to announce the successful completion and launch of Merrifield City today.

It was a pleasure to be a part of another successful project with QIC and NH Architecture, as well as QIC’s JV partners MAB Corporation and GPC.

Maben Group and the Merrifield City team would like to thank all of our hardworking subcontractors that were involved in the project. Without their tireless efforts, this fantastic end result could not have been achieved!

Photos by Lucas Dawson.


November 30, 2020




Maben Group are pleased to announce that we recently secured the fitout for the Victorian Government’s Department of Transport Workplace and Customer Service Centre as part of the EastCo development.

The EastCo team welcomed a site visit from the Department of Transport last week, and look forward to delivering another successful project in 2022! #themabenedge


November 24, 2020






Almost there….

We’re very proud of our Merrifield team who have shown great effort and productivity this year!

And now, with the last of the finishing details underway, our team are officially counting down the days to Wednesday 2 December when the doors open for business at Merrifield City!

Go Team #themabenedge


November 23, 2020





The EastCo project is moving along well with the two cores now up to Level 5!

Parts of the ground suspended slab have been poured and formwork is now well underway to the Mezzanine level.

In the lead up to the Christmas break the team are on track to complete the mezzanine concrete pours and begin formwork to the Level 1 suspended car park.





‘M’ is for MABEN!

With the first of the Merrifield City letters being installed and the Coles fit-out nearing completion, the team at Merrifield City are gearing up for the final push prior to opening!










With the end in sight, the Highpoint team have continued to make great progress!

Floor demolition and timber flooring infill works are complete, whilst the tiling and column cladding are well advanced throughout the project.

The awnings to the North Mall are taking shape with the final coat of paint and the Rimex panels now being installed at high level.




Maben Group has successfully handed over the Porsche Training Facility for fitout works to commence – project milestone achieved!

Inside the Volkswagen building we are seeing some fantastic progress with wall framing and service rough in well underway and the façade beginning to take shape.

Externally the asphalting is complete, allowing the concrete footpath, Quarantine Bay and fencing works to progress.


October 15, 2020







The EastCo team have finalised the gantry installation and gantry site amenities.

In-ground footings are complete and the first concrete slab has been poured for the lower ground/end of trip area.

The site also welcomed it’s first delivery of precast panels & columns this week and the team are excited to see the two 2 cores continue upwards – go team!


BACK TO TOP