Maben Group has successfully handed over the Porsche Training Facility for fitout works to commence – project milestone achieved!

Inside the Volkswagen building we are seeing some fantastic progress with wall framing and service rough in well underway and the façade beginning to take shape.

Externally the asphalting is complete, allowing the concrete footpath, Quarantine Bay and fencing works to progress.


October 15, 2020







The EastCo team have finalised the gantry installation and gantry site amenities.

In-ground footings are complete and the first concrete slab has been poured for the lower ground/end of trip area.

The site also welcomed it’s first delivery of precast panels & columns this week and the team are excited to see the two 2 cores continue upwards – go team!


October 12, 2020




It is with great pleasure that we announce that the i.Co Richmond project has been awarded to Maben Group!

Inspired by Richmond’s rich industrial heritage, i.Co Richmond will consist of 14 fully self-contained three-storey offices. This office project involves the demolition of three existing buildings followed by construction of the boutique workplaces and associated car parking.

Maben Group are extremely excited to be working closely with Wilmac Properties and Watson Young and look forward to delivering a successful project!





Check out the latest progress from the Woodlea Town Centre! It’s great to see our team in Aintree have continued to make good progress despite their reduced workforce under the COVID-19 working restrictions.

Well done team!


September 21, 2020





Over the past four weeks under the current working restrictions, our team have focused their attention on the detailed façade at Merrifield City.

Gather Advanced Photography visited site last week to capture their progress.

We think it looks great! What do you think?


September 11, 2020




Exciting times on site at EastCo, with the recent addition of the tower crane to the Ringwood project!

Gantry and site shed installation is now underway, and concrete pours to start soon.







Its been a busy month for our Essendon Fields team. The Porsche building is nearing completion with only floor and wall finishes to be installed!

And, inside the Volkswagen building the concreters have completed their works allowing the erection of high level services and wall framing to commence.

Externally, the first layer of rock has been installed to the rear car park following completion of the retaining wall.


August 27, 2020



The EastCo site has been steadily progressing with bulk excavation works now finished and detailed excavation and structural footings nearing completion.

The team also recently installed the tower crane base which is now ready for the upcoming crane erection – keep an eye out!

Final preparations for the site gantry are underway and installation is set to begin at the end of the month.





Focus has shifted to the North Mall as the Highpoint team achieve another milestone with completion of the Level 2 tiling demolition works! Above on Level 3, the timber rod awning installation is nearing completion which has allowed the final stage of floor tiling to commence.

The Centre Court final touches are also underway with the spotted gum column cladding installation commencing, which really complements the design!







With the new Melbourne working restrictions underway for construction, the Merrifield team continue to work well on site and remotely.

Before the restrictions kicked in, the team were very pleased to see the completion of the Coles box. They have since continued on with the retail component of the development with the installation of the shopfront glazing last week.