Works on site are progressing rapidly at our commercial office development located in the heart of Ringwood.

Structural works are complete, with the fa├žade and internal fitout works are well underway.


February 19, 2020






In-ground concrete is nearing completion at Merrifield as the boys are gearing up for the first of many slab pours this week.

Our services trades are moving along nicely, working hard to keep ahead of our concrete crew.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=drgZGgoj”

Photos by Gather Advanced Photography.







After a well deserved break the team at Highpoint have had a good start to the year with the commencement of ceiling demolition to Zone 1 Level 3 in preparation for the new feature awning.

Decommissioning of the Zone 3 Travellators and Escalators has commenced, prior to two new sets of escalators being installed in the coming months.

Zone 3 Level 3 is nearing completion with the Big W Node ceiling demolition being complete, and ceiling finishes commencing.

Progress to Centre Court has seen painting of the feature awning in preparation for the timber batten installation.








The team at the new Merrifield City project are well underway on site having completed all concrete footings to the Coles box and are now progressing well in the retail area.

In-ground services are also being completed in the new fresh food area.

Stay tuned for Precast and Steel!