It’s been a busy couple of weeks at the iCo Richmond office development with the erection of precast panels and structural steel a main focus for our site team.

Developed by Wilmac & inspired by Richmond’s rich industrial heritage, i.Co Richmond will consist of 14 individual offices amongst 3 three-storey buildings upon completion.

We can’t wait to see this exciting development progress!



The Highpoint team have completed their first milestone of the project following the successful removal of the dual existing escalators within the center of the tenancy!

Demolition works are also well underway following the completion of the new intertenancy walls and loading dock separation works.





The iCo Richmond office development continues to progress at a solid pace with the recent completion of footings site wide. The team are now concentrating on the installation of full height precast panels and concrete pours. In-ground service works alongside the installation of structural steel, also continues to progress.

Great effort by our team!