June 30, 2021




With the concrete structure complete on level 9, and level 10 formwork underway, our team are inching closer and closer to top out!

Services rough in is underway on ground to level 4, and the set out of level 5 has commenced.

We can’t wait to see our team complete the structure and for the facade works to begin.



Congratulation to Greg who celebrated his ten year working anniversary with Maben earlier this month!

Thank you for your many years of wonderful service.





It has been a busy few weeks for the David Jones / Kmart project team with the completion of internal demolition and escalator infill works.

Service trades rough in is well progressed following the completion of the soffit painting.



We are pleased to announce that the Highpoint Target Backfill (Stage 1) project has been awarded to Maben Group!

Stage 1 of the Target tenancy reconfiguration includes the demolition of an existing Target and the creation of two new tenancies.

Works have commenced and an opening date is scheduled for October 2021.

Maben Group look forward to working with The GPT Group, Cadence Australia, i2C Architects, Baigents and ADP Consulting on another successful Highpoint project





Precast panel & structural steel installation is now complete for two of the three future office buildings at iCo Richmond, whilst concrete works, services and masonry continue throughout the site.

With the big items lifted and installed to the back of the development, our team are now focused on the installation of precast panels for the third building located on the western boundary.

Great progress by our team!


June 2, 2021

The EastCo project is nearing its top out height with the level 9 formwork now underway and only two floors to follow.

Services rough in and wall framing has begun on the lower floors, carpark façade screens are due to begin shortly and the curtain wall façade to follow closely.

Great work by our EastCo team.