During the course of the last month, the Buxton Contemporary project has made significant progress in all areas of the site.

The administration and office areas in the Heritage building have had walls plastered, doors installed, and new and existing floors prepared.

Joinery units have started to arrive on site with the toilet vanities, reception, and kitchen units installed.

The art hanging wall plastering is progressing sequentially through the heritage building, new building ground and level 1 gallery areas.

Externally, the facade cladding at high level is almost complete. The lower level cladding has commenced and will be continuing along the southern elevation.