The first stage of the Level 1 main concrete slab at Buxton Contemporary has been poured. Concreters are continuing to set up the propping and formwork for the final pour of the Level 1 concrete slabs.

Other progress on the structural works this month include the final installation of precast panels and structural steel beams for the new loading dock area.