External cladding works on the high level facade are mostly complete and the preparations for the low level cladding have now commenced.

The perforated plaster raked ceilings have been painted in the heritage gallery and the exposed ductwork installation has begun.

Mechanical and fire services have been roughed into Level 1 of the New Gallery, and the gallery art wall framing is following closely behind.