The site team at Colac Plaza are excited to see the first section of the Coles slab prepped, with the pour scheduled for tomorrow.

Recent works have included the installation of the Vapour Mitigation System that is laid in a bed of rock beneath the suspended slab. The VMS contractors will continue to work ahead of the concrete prep as pours progress.

The plumbers continue to work their way around the prep areas of Coles and we’ll see them move into the tenancies before long.