The Colac Plaza team have hit another milestone with the standing of the first precast panels to the Coles box during the past week.

Due to restricted access on the site’s southern boundary, slab pours have had to be strategically sequenced to enable crane access for the installation of these initial panels.

The team now continues to push through the remaining pours of the Coles slab, and will concurrently install the precast panels to the perimeter of the main box over the coming weeks.

Meanwhile, in-ground services to the tenancies of Stage 1 near completion, with the detailed preparation for the slab to commence during the next week.