The team at Coles Aurora have started the New Year well with the job progressing on all fronts.

The team is working hard to have Aldi ready to hand over to the shopfitting team in February with all internal slabs poured and roof now complete.

Coles is looking great with the selling floor slab almost completely polished and internal painting and services tracking well.

Building B footings are in the ground with the slab to be poured and precast panels to be erected in the coming weeks. Building C & D internal framing is going up and the roof is ready to be laid.

Tenancy 16 bored piers and capping beam were poured at the start of the year and precast has been erected.

Coles Express has all the in-ground services laid and the ground is being prepped for the slab to be poured soon.