Next Wednesday marks the 800th Coles store opening in Australia and the team have been working very hard to have the Coles Aurora project ready!

The Coles Express store has been handed over to the shopfitters and the external works are in the final stages with external cladding complete, fuel pumps installed and the pylon sign erected. First fuel fills are due this week.

All pavements have now been laid along Piazza Way with asphalt and stone feature bands to be laid. The pylon signs have been erected and Aldi signage installed. Coles and smart parking signs will be installed this week. The gym cladding and glazing is now complete and the lift is now being commissioned.

Landscaping is progressing well with a majority of the carpark plants now in the ground and Coles Express and external planter beds ready for planting.