The team at Coles Aurora have been working hard in the lead up to Christmas to have the project in a good position to come back to in the new year.

The precast for Coles, Aldi and Building D has been erected and the Coles roof has been laid.

The final slab pour for Coles front-of-house is going down in the next couple of days.

The number of trades on site is growing with mechanical duct work arriving on-site, wall framing has started erection in the Coles amenities areas and masonry walls have started to go up in the plant room.

The authority sewer is 90% complete down Piazza Way and the civil contractors have started on the retaining wall of the car park.