The back of house floors have been sealed and line marked with all joinery installed to the cleaners area lunch room and team office.

Externally, cladding works are underway with the aluminium timber look fins installed to the north façade, and alucobond being installed to the entry canopy. Signage installation has commenced this week too!

While Dan Murphy’s begin their internal fitout we are continuing the external works with asphalt pours to the carpark scheduled for this week.