The EastCo team topped out last month which was a great milestone to achieve! The focus has now shifted with the commencement of works for the façade installation last week. Carpark perforated screens are underway and curtain walling is off to a good start. Internally, installation of all five lifts has begun and internal services rough-in is charging along.

Great progress by our team in Ringwood!