With the recent opening of the new Big W escalators to the public, the Highpoint team have continued momentum with areas of the Centre seeing significant progress.

In Zone 3 tile demolition has reached the Level 2 Big W node whilst the tilers are busy on Level 3 completing the final infills against the new balustrade.

Demolition works to the Zone 1 Level 3 bulkhead are now complete, and new bulkheads to tenancy shopfronts are starting to take shape, with framing ready for spotted gum cladding and feature awning installation.