The Highpoint team have now commenced the major task of tile demolition, with the first night seeing approximately 80m2 of tiles removed. Installation of the new tiles is scheduled to commence in 2 weeks, and will follow the demolition through the mall.

Structural steel erection is continuing with Big W Node 5 being completed ready for bondek installation for our first concrete pour of the project.

Finishes are progressing well in Zone 3 Level 3, with wallpaper and painting to commence shortly.

PT truncations to the new Water Feature Node have been completed, and slab demolition well underway.