With only 1 month to go at Holden Essendon Fields, the job is starting to take shape. The Holden pylon has been installed, the workshop slab preparation is complete and the first coat of epoxy has been applied.

Internally the Showroom overhead services are complete allowing the tiling to flow through the selling floor, whilst the back of house joinery is being installed.

Externally the signage and remainder of the cladding is due to arrive next week and asphalt will be laid early June!