The Craigieburn Junction team are drawing closer to completion!

GAP Photography visited site recently to snap the project in its final stages.









Works are progressing quickly at 7 Ormond. Outside, the roof and fa├žade glazing installations are complete, with the carpark, kerbs and landscaping to commence in coming weeks.

Internally plasterboard walls are being prepared for the first coat of paint and all service-rough ins are nearing completion.







Level 5 pour began on Monday with the team standing panels on level 5 tomorrow.

Set out and framing is underway on B1, block work to B1 and ground floor continues and high level services are starting on B1 to level 1.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=MjBkNxBr

Photos by Gather Advanced Photography.










With only 1 month to go at Holden Essendon Fields, the job is starting to take shape. The Holden pylon has been installed, the workshop slab preparation is complete and the first coat of epoxy has been applied.

Internally the Showroom overhead services are complete allowing the tiling to flow through the selling floor, whilst the back of house joinery is being installed.

Externally the signage and remainder of the cladding is due to arrive next week and asphalt will be laid early June!



Structural steel is almost complete, the roof is on and capping and flashing works are up next.

Alucobond cladding also is progressing well.

The staff amenities works have begun upstairs and the Porsche Brighton team will relocate their lunch room and office shortly in order for demolition to begin.

Terrific progress team!







GAP Photography visited site earlier this week to capture the busy project in Ocean Grove.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=O0wx7W8Y&fbclid=IwAR38qFtar8tGK3PKqarEAor5ySlVH7uFjH_RrVhDaMUGRLUI9yftxNsyVHs






Structural steel is now complete and all precast panels have been installed.

The Bondeck to Level 1 is underway with the first Level 1 slab pour finished.

Roof installation and facade works to begin shortly.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=6re54Zmr

Photos by Gather Advanced Photography.








Craigieburn Junction is starting to take shape with the commencement of landscaping and external pedestrian paving works.

Base build works are nearing completion and the site team are gearing up for their first stage of handovers!

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=ZjQxyLNY

Photos by Gather Advanced Photography.





The Albert St team started pouring level 1 yesterday.

Gantry installation began today, and the next batch of precast is due for delivery on Monday!

Terrific progress.






Following the completion of the structure and roof, the showroom concrete slabs have been poured with the workshop concrete pours to follow this week.

High level rough in to showroom has commenced and is progressing well, with external cladding and wall framing to follow.

Photos by GAP Photography.


BACK TO TOP
BACK TO TOP