GAP Photography visited site earlier this week to capture the busy project in Ocean Grove.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=O0wx7W8Y&fbclid=IwAR38qFtar8tGK3PKqarEAor5ySlVH7uFjH_RrVhDaMUGRLUI9yftxNsyVHs






Structural steel is now complete and all precast panels have been installed.

The Bondeck to Level 1 is underway with the first Level 1 slab pour finished.

Roof installation and facade works to begin shortly.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=6re54Zmr

Photos by Gather Advanced Photography.








Craigieburn Junction is starting to take shape with the commencement of landscaping and external pedestrian paving works.

Base build works are nearing completion and the site team are gearing up for their first stage of handovers!

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=ZjQxyLNY

Photos by Gather Advanced Photography.





The Albert St team started pouring level 1 yesterday.

Gantry installation began today, and the next batch of precast is due for delivery on Monday!

Terrific progress.






Following the completion of the structure and roof, the showroom concrete slabs have been poured with the workshop concrete pours to follow this week.

High level rough in to showroom has commenced and is progressing well, with external cladding and wall framing to follow.

Photos by GAP Photography.





The Richmond team have begun’the ground slab pour.

Precast is set for delivery on Thursday!


February 22, 2019

We are excited to announce that Brad Taylor has joined Maben Group as Mabens’ Small works and Building Repairs Manager.

Brad has accumulated over 20 years’ experience at Probuild in various site roles and was involved in a wide range of projects in different sectors.

His vast experience is of a great asset to Maben.

Welcome to the team, Brad!





The Bundoora team completed the final ground slab pour late last week.

Precast panels are scheduled this week and structural steel will follow soon after.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=l0lEqdVY










GAP Photography visited site earlier this week to capture the team’s steady progress.

The large scale project is powering along!

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=WjGnvdeY






It’s been a been a big start to the new year at Kingston Village Ocean Grove!

With lime stabilisation now complete, in-ground services are well underway to all areas and footing works are in progress to the Woolworths and Dan Murphy sites.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=mrpy4nO0


BACK TO TOP
BACK TO TOP