We have reached an exciting milestone at Highpoint Shopping Centre with the delivery and installation of the two new Centre Court escalators!

Following completion of the ceilings within Zone 3 Level 3 the team have commenced tiling works, whilst on Level 2 the ‘Honeycomb’ ceilings are progressing well.

Zone 1 is starting to take shape following the structural demolition of the first of three Juliet balconies and the new water feature structural steel erected with formwork and concrete to follow.



It is with great pleasure that we welcome Luke Maccora to Maben Group as our Commercial Manager.

Luke commenced with us in February and has come on board after a successful career in Contract Management.

We are very pleased to have you on board, Luke!








The Kingston Village team recently handed over Woolworths and Dan Murphy’s for the commencement of shop fit out works.

The tenancy handovers for the remaining retail spaces are now underway.

Final preparation of the carpark sub base has begun in readiness for asphalt works in the coming week.


October 11, 2019

We are pleased to welcome Jasmine Tisdall.

Jasmine commenced in August in the accounts team as an Assistant Accountant, after recently completing her Bachelor of Business (Accountancy) at RMIT.

Welcome to the team Jasmine!





GAP Photography visited site earlier this week to capture the busy Richmond project.

The team are working hard in the lead up to completion!


October 9, 2019

We are pleased to welcome Josh Orchard to Maben Group.

Josh has 15+ year industry experience and during this time he has working on a variety of projects ranging from $2M – $25M.

He joined Maben as a Site Manager back in February and is part of the Kingston Village Shopping Centre team in Ocean Grove.

Welcome to the team, Josh!





The team out at Highpoint have been working hard across all areas of the Centre. The ‘Honeycomb’ ceiling is starting to take shape onsite with templating, perforated panels and lighting channels commencing.

Painting of steel and skylight frames in Zone 1 is progressing well.

Ceiling finishes to Zone 3 Level 3 are nearing completion, with the last of the wallpaper being installed in the coming days.

This has allowed the screeding works to commence with the tiling to follow.




The Eastland Team are progressing well with formwork and bondeck underway throughout in preparation for the first slab pour.





The Highpoint team have completed another milestone with their first concrete pour of the project, involving 20m3 of concrete installed across multiple locations within the Centre.

The completion of the concrete pour has allowed the mast climber to be installed in Centre Court providing access to high level ceiling works over the existing void.

The scaffold catch deck has now been dismantled following the successful completion of the concrete demolition for the future Water Feature as we prepare for the structural steel installation.

Tile demolition and ceiling finishes are progressing well in Zone 3 Level 3, while on Level 2 the templates for the feature ‘Honeycomb’ ceiling have commenced.












Final commissioning works are underway to Woolworths and Dan Murphy’s in readiness for handover.

Main mall area works are nearing completion and main carpark works are in progress.

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=o04pg6R0″

Photos by Gather Advanced Photography.


BACK TO TOP
BACK TO TOP