A beautiful morning at the Yarra Yarra Golf Club for team Maben Group playing in the Challenge Robert Allenby Golf Day Fundraiser!

Check out http://www.challenge.org.au/ for more information on Challenge, and how you can get involved and support kids with cancer.




The Woolworths trolley bay, switchroom and tenancy storeroom slabs have been successfully poured with the precast panels scheduled to arrive next week with the structural steel to follow.

The new Norman Street car park entry sub base work is complete and, following on from the completion of the final stage of the structural demolition, the remaining civil works for the shopping centre extension have progressed well.





The Pacific Epping Quest team have completed the first pour of level 3, and are currently installing precast.

Ground floor strip out has begun, along with the second level 3 pour.


November 11, 2017




With in-ground works nearing completion and ground slabs well underway, the CubeOne project is now officially out of the ground!

The precast concrete core has progressed which has opened up the site for our structure contractor this week.

And the design team have been engrossed in the shop detailing process as the site team begin to turn their focus to the concrete structure in the lead up to Christmas.









Debenhams officially opened for trade on Tuesday 24th October!

Maben was pleased to handover the St Collins Lane flagship store, with the complex project delivered one month ahead of schedule thanks to the hard work and long hours of our Site team and all of our Subcontractors.

It was a pleasure to be a part of another successful project with the Basso Project Management and Clarke Hopkins Clarke, and working closely with JP Morgan and Project Strategy.

Photos by Lisbeth Grosmann.







Clyde K-Mart Tyre & Auto was handed over to the K-Mart fit out team on Monday October 30th.

In the lead up to hand over, the team progressed with great speed to complete the interior of the building, as well as the car park & external KTAS sign writing to be ready for fit out.

We would like to thank all of our sub-contractors for their efforts to deliver another successful project.

Maben Group look forward to the grand opening on November 27th!








During the past two weeks the Pacific Quest Epping team have been busy prepping for the level 2 concrete pours.

Pour 1 of level 2 is now complete, with pour 2 scheduled for tomorrow.

The level 3 precast cores have been installed and the first level 3 pour is set for after the Melbourne Cup Long Weekend

And the plumbers have been digging and installing in-grounds outside the job for incoming services for the hotel.



Follow this link for a 9 News article, with a clip from Current Affair featuring drone footage of our Quest project at Epping: http://www.9news.com.au/national/2017/10/03/18/30/bargain-hunters-already-scenting-boxing-day-opportunity-at-shop-and-stay-hotels








This month all structural works have been completed at the Kennington Village Stage 2 expansion project.

External pavement and cladding works have progressed, with the roof to the Pad site retail building complete.

All three buildings are tracking for completion and handover to fitout contractors at the end of November.









All the major works on site at Buxton Contemporary have been completed.

The project is now entering the testing and commissioning phase of the building services.

The team all put in a fantastic effort in the lead up to completion. We would like to thank all of our hardworking subcontractors for their efforts over the past couple of months!


BACK TO TOP
BACK TO TOP