Footings and in ground services are progressing well at Craigieburn Junction, with the ground slab for the first of five buildings nearing completion this week.

Our site team are eagerly waiting the delivery of the first precast panels and structural steel which is expected in the coming weeks!


August 6, 2018

Maben Group welcomes Chris Mikha to the team in the role of Contracts Administrator.

Chris graduated in 2015 from RMIT with a Bachelor of Applied Science (Construction Management). He began his CA career soon after, working on projects from $1M – $5M in the residential and educational sectors.

We are pleased to have you on board, Chris.



We are pleased to welcome Alex Panaccio to Maben Group in the role of Contracts Administrator.

Alex graduated from RMIT in 2010 with a Bachelor of Applied Science (Construction Management). He has over 8 years experience on a range of projects from $1M to $20M within high-end residential, education and the aged care sector.

Welcome aboard Alex!







This week, the team have been building the bench for upcoming pours. Formwork has also begun, and precast is set to go up next week.

The next stage of demolition will begin later this month.










The back of house floors have been sealed and line marked with all joinery installed to the cleaners area lunch room and team office.

Externally, cladding works are underway with the aluminium timber look fins installed to the north façade, and alucobond being installed to the entry canopy. Signage installation has commenced this week too!

While Dan Murphy’s begin their internal fitout we are continuing the external works with asphalt pours to the carpark scheduled for this week.










A few photos taken last Friday of the busy Featherbrook Stage 2 project.

The team have put in an a huge effort in the lead up to today’s shell completion.

The project is now ready for the fit-out component.

Well done Daniel, Ryan, Matt and thank you to all our hardworking Subcontractors.








The external structural steel is approaching completion and the rear entry structural steel canopy is currently being erected.

Wall framing is advancing in all areas, plaster sheeting is following close behind and the new mezzanine concrete slab is ready to be poured.

Great work team!









Construction work has commenced at Craigieburn Junction!

Footings and in-grounds are well underway with Glenn and our site team starting preparation for our first ground slab pour.

Photos by Gather Advanced Photography.



It’s all happening at the Dan Murphy’s Pacific Epping Project!

Internally works continue to progress with the plaster and painting works to the trading floor and back of house areas well underway.

The cool rooms have been installed and the light fittings are being installed to the exposed cable tray.

Externally, our civil contractors have begun to prep for asphalt and pavements and kerbs are being installed to the car parking areas.






The Quest Pacific Epping project is now in it’s final stages and ready to be completely open to the public next Monday!

Today the team handed over the Urban Diner extension area, ready for the food tenancies to open to the public for trade.


BACK TO TOP
BACK TO TOP