September 11, 2020




Exciting times on site at EastCo, with the recent addition of the tower crane to the Ringwood project!

Gantry and site shed installation is now underway, and concrete pours to start soon.







Its been a busy month for our Essendon Fields team. The Porsche building is nearing completion with only floor and wall finishes to be installed!

And, inside the Volkswagen building the concreters have completed their works allowing the erection of high level services and wall framing to commence.

Externally, the first layer of rock has been installed to the rear car park following completion of the retaining wall.


August 27, 2020



The EastCo site has been steadily progressing with bulk excavation works now finished and detailed excavation and structural footings nearing completion.

The team also recently installed the tower crane base which is now ready for the upcoming crane erection – keep an eye out!

Final preparations for the site gantry are underway and installation is set to begin at the end of the month.





Focus has shifted to the North Mall as the Highpoint team achieve another milestone with completion of the Level 2 tiling demolition works! Above on Level 3, the timber rod awning installation is nearing completion which has allowed the final stage of floor tiling to commence.

The Centre Court final touches are also underway with the spotted gum column cladding installation commencing, which really complements the design!







With the new Melbourne working restrictions underway for construction, the Merrifield team continue to work well on site and remotely.

Before the restrictions kicked in, the team were very pleased to see the completion of the Coles box. They have since continued on with the retail component of the development with the installation of the shopfront glazing last week.





The Woodlea team are approaching their first project milestone with the substantial completion of Coles.

Coles is progressing well whilst the entire team continue to work within COVID-19 guidelines to keep the project and community safe.

Great effort during these difficult times. Well done Team Woodlea!







Progress continues at Merrifield City and GAP Photography visited site earlier this week to capture the busy Donnybrook Road project.

Coles is coming together well and the saw tooth roof cladding to the retail area is now complete.

Great effort by our Merrifield team who continue to maintain productivity on site whilst managing the winter & COVID-19 challenges over the recent month.


July 27, 2020





Works have begun at EastCo and the team are excited to have the project underway!

Site establishment is complete, building foundations have commenced and the team recently began bulk excavation works.

We look forward to watching this project progress over the coming weeks!









We are delighted to announce the completion of the Eastland Office Development!

It was a pleasure to be a part of a successful project with QICGRE and to work closely with Turner and Townsend, ACME Space and Peddle Thorp Architects.

We would like to thank our hard working team for their contribution and all the subcontractors for their efforts.

Thank you!





Progress continues at Essendon Fields with our construction team completing the external glazing, painting and cladding works to Porsche. Internal finishes are now underway.

Right next door, the Volkswagen structural steel, precast and roofing works are complete and the team have prepped the next stage of concrete slabs in readiness for upcoming pours.

Great effort by our team!


BACK TO TOP
BACK TO TOP