September 22, 2021


Over the past fortnight, our team have successfully completed roofing works and the final internal slab pour.

Internally progress has been steady with the installation of services, wall framing & sheeting, painting, balustrades and feature bulkheads.



The Highpoint Aesthetic Mall Upgrade Phase 2 team are off to a great start in the Target Mall and Node 6.

Following completion of the ceiling demolition late last month, the service rough in, lighting channel install and ceiling framing are ready for finishes.




Where the old meets the new! The Maben Windsor Primary School team were very excited for the recent arrival of structural steel for the school’s upgrade.

Over the coming month the team will see the completion of structural steel and the start of roofing, as well as masonry to the façade.




Despite the current challenges surrounding the building and construction industry, our Highpoint team have made great progress!




Behind the hoardings, demolition works are progressing well. The space is looking tidy and well on its way to being ready for a new Coles!

Concurrently within the main mall, the team successfully installed rotunda travelators over a four night period. Commissioning works will be underway shortly to provide shoppers access from the Basement carpark to Ground and Ground to the outdoor carpark above.





The completion is in sight for the future Kmart tenancy at Highpoint Shopping Centre with all of the finishes progressing well. The current lockdown has slowed the pace but our team remain on track for completion in the next few weeks!


August 24, 2021

Maben Group welcomes James Tsafkas to the team!

James joins us in the role of Project Coordinator. He is currently studying a Bachelor of Applied Science (Construction Management) (Honors) at RMIT University.

Welcome aboard, James!


August 19, 2021


The iCo Richmond team have almost finished the structure with just one more level and the driveway slabs to be poured. The install and completion of the second roof went well and the final roof is scheduled for completion by the end of this month.

Architecturally window installation is underway, handrails, balustrades, bulkheads and walls continue and brickwork is nearly complete.

Amazing progress by our team!



We are pleased to welcome Ben Podger to Maben Group in the role of Site Manager!

Ben is a dedicated construction professional with over 20 years of construction experience. He began his career as an Apprentice Carpenter before moving through the commercial construction ranks to the role of Site Manager. He has a strong track record on a range of new build projects, and joins us with valuable experience in structure, formwork, civil, facade, fitout and finishes.

Welcome to the team Ben!


August 16, 2021



The EastCo team topped out last month which was a great milestone to achieve! The focus has now shifted with the commencement of works for the façade installation last week. Carpark perforated screens are underway and curtain walling is off to a good start. Internally, installation of all five lifts has begun and internal services rough-in is charging along.

Great progress by our team in Ringwood!


BACK TO TOP
BACK TO TOP