It has been a busy 2 weeks at Essendon Fields.

Porsche building
Structure is now complete and wall framing service rough in has commenced. Externally, the louvre outriggers and aluminium window frames are also complete.

Volkswagen building
Stage 1 roof structure is now complete and Stage 2 is well on the way. Our roofer has commenced and we are keen to have the building water tight by our next update!