The Quest team successfully installed the precast lids for both the stair and lift core the first week back from holidays.

Prior to Australia Day the service trades were busy on levels 1 and 2, stripping of formwork was underway, level 6 structural steel work was almost complete and the setting out of walls on level 2 and framing of level 1 had begun.