The Quest Pacific Epping team are progressing well.

Window frames to level 1, 2 and 3 have been installed. Sub-sills and sub-heads on level 4 are now currently underway.

Plaster has started to the ceilings on level 2 and walls on level 3, with stoppers and ceiling grid following behind. The team has also begun framing on level 5.

Last but not least, civil works kicked off last week behind the job.