We have had a very busy month with the building now completely locked up, energised and all auto doors and mechanical units commissioned. Light fittings are on target to be completed this week. Cleaners are commencing their initial clean next week and remaining floor finishes to commence shortly. The club is very excited to get the keys to their new building in September.