In the Coles Tenancy at Clyde Village this week, all Mechanical hard ducts and spiro have been installed and completed. The fire sprinkler system has also been installed (including the Liquorland). All block work to the selling floor back of house is complete, cool room & freezer construction has commenced, the electrical rough in is well advanced and the Askin Panel roof is now laid.