The team at Coles Aurora have achieved substantial completion of the Coles supermarket and specialty tenancies.

Piazza Way, building facades, the car park, gym and Coles Express are now the priorities.

Civil works have been a big focus in the past couple of weeks with preparation of Piazza way moving along nicely.

External cladding has begun on Buildings A, B, C & D with timber look cladding to buildings A & C and perforated metal cladding to Buildings A, B & D all well underway. All shopfronts have now been installed with the exception of the Gym and Coles Express and external painting is progressing well.

Carpark final levels are close to being achieved and a majority of the kerbs are now installed with preparation of tarmac and footpaths to follow in the next few weeks.

Both the ground floor and first floor slab of the gym have now been poured, the external wall framing has commenced, and the external brickwork and all internal stairs are complete.

The Coles Express shop and canopy roofs are laid, the internal wall framing is complete and shopfronts are due next week. External slabs are ready to be prepped and poured in the coming weeks.