Works have continued at a rapid pace despite a spate of inclement weather over the past couple of weeks. Our second post tensioned slab is due to be poured this week with formwork moving ahead at a rapid pace.
We have seen our first two deliveries of precast which has also transformed the site and provide some more structure.
Structural steel will be moving ahead in the next few weeks to close out the structure.