The Kingspan panel roofing commenced last week at a rapid pace. Utilising 2 cranes to tag team the sheet lifts increased the rate of installation dramatically. The main focus in the coming weeks is to get the Coles box watertight, and the only thing that could hold us back would be bad weather.
The new substation was successfully changed over on the weekend and the demolition of the existing substation has commenced, which will allow us to handover the Coles loading dock.