Overhead demolition works are nearing completion with the majority of the column claddings and ceilings now removed. The plasterboard surrounds around the existing structural beams are being raised to make way for the new feature ceiling beams due onsite later next week. The service contractors are also progressing well with the cable trays and sprinkler alterations.