Ormond Square resumed in 2015 with the completion of the structural steel columns. To date, all roof purlins and the perimeter fascia truss have been installed. With the concreting works nearing completion, formwork stripping of level 2 is now complete with the service trades commencing on services rough-in. Preparations are being made for the scheduled next floor strip out.