Progress at the Dunes is rolling along well.

The Woolworths box has now been handed over and fitout from Woolworths side of things is well underway.

Maben have handed over one of the sixteen surrounding tenancies in which Bakers Delight will shortly commence their store fitout. The remaining tenancies have seen base build handover this week with individual tenants commencing their shop fitouts.

External works are continually progressing and the team are happy to have a sealed surface with 75% of asphalt now laid in the Centres main car park.

Eave sheeting is approaching completion, external cladding and roof cappings are continually battling the weather, landscaping works have kicked off with the installation of tree protection bollards to the car park area and garden bed construction is upcoming.

Concreting to the centres footpaths continues with the western footpath prepped and currently being poured in sections. The final footpaths to the north in front of the centre mall are to follow this week.