External painting to the College Street elevation is nearing completion, now that all framing has been completed. Alucobond box sections for the signage has been installed, with the lighting ready to be fitted off.

All structural steel is now complete, with the roofing contractors completing the last section of roof sheets this week. Steel shop fronts are progressively being installed to 20 tenancies which is paving the way for the glazing, plastering and painting contractors to carry out their works.