It has been an action packed week on our Woolworths Keysborough project.

Derryn and the team have completed the bulk excavation of the car park, which is now ready for the sub-grade preparation. The back of house Woolworths slabs have also been poured and we have taken delivery of the first 32 precast panels to the Woolworths box.

With summer finally breaking through this project is expected to progress quickly!

Back