We now have full access to the 4000sqm Woolworths box, following completion of the Stage 2 demolition and erection of the perimeter blockwork walls. We have had 3 refrigeration case deliveries so far, with another 2 deliveries due this week. The trading floor ceiling grid is progressing well, so too the preparation area and back of house area rough in.