The refrigeration racks, electrical switchboards and condensers have all been lifted onto the new plantroom slab and condenser deck, with the mechanical ductwork scheduled for erection tomorrow.

Stage 2 of the demolition has commenced following the internal mall hoarding being altered and the pharmacy relocated.