Craigieburn Junction is starting to take shape with the commencement of landscaping and external pedestrian paving works.

Base build works are nearing completion and the site team are gearing up for their first stage of handovers!

Click on this link for a 360 site photo:

https://viewer.hangar.com/360?productId=ZjQxyLNY

Photos by Gather Advanced Photography.





The Albert St team started pouring level 1 yesterday.

Gantry installation began today, and the next batch of precast is due for delivery on Monday!

Terrific progress.






Following the completion of the structure and roof, the showroom concrete slabs have been poured with the workshop concrete pours to follow this week.

High level rough in to showroom has commenced and is progressing well, with external cladding and wall framing to follow.

Photos by GAP Photography.





The Richmond team have begun’the ground slab pour.

Precast is set for delivery on Thursday!