Congratulations to our Highpoint team who have successfully completed the works to the Big W escalators.

They were opened this morning by The GPT Group Assistant Operations manager, Graeme Smith.

Well done team, and thank you to all our subcontractors.





Our Merrifield team are making great progress on site with the roof underway – just in time for winter – to the Coles box!

Structural steel is also due to commence next week to the retail area.



Congratulations to Howard Turner on his ten year working anniversary with Maben Group!

We would like to take this opportunity to thank Howard for these past 10 years of company loyalty – his continuous hard work and dedication to Maben is greatly appreciated.

Thank you for your many years of wonderful service.






The Woodlea team have gathered good momentum despite challenging weather conditions over the past few weeks.

The structure of the Coles box is now complete with all precast and structural steel erected. Works for the Coles roof are scheduled next, allowing for the preparation of internal concrete slabs to commence.

All in-ground services have been installed in the adjacent tenancy spaces of the Lot 1 building surrounding the future Coles supermarket. Precast panels are underway and the first concrete slabs have been poured on the West side where the future medical centre and office spaces will be located.

On the North East corner of the project, earthworks are complete and footings are underway for the Lot 2 commercial building.

Finally, on the North West corner of the project earthworks are complete for the Lot 3 cafe park building.








It has been another busy month at Highpoint for the Aesthetic Upgrade team! Zone 1 ceiling demolition works are nearing completion, in turn enabling bulkhead framing to progress which is now ready for cladding. Glazing to the balustrade in Zone 1 has also progressed well.

In Zone 2 and Centre Court, the installation of the timber batten awnings have begun following the completion of the new tiling. And the future Hoyts escalator structural works are well underway in preparation for the delivery of the dual escalators in the coming weeks.






The Woodlea team have been busy over the last few weeks with the installation of precast panels and structural steel for the Coles box.

This week they successfully completed the concrete slab pour for the future Medical Centre.



We are pleased to welcome Donny Smarrelli to Maben Group.

Donny joined our team in February in the position of Leading Hand.

Welcome aboard, Donny.



We are pleased to welcome Joe to Maben Group in the role of Contract Administrator.

Joe joins us with solid construction industry experience. Whilst completing a Master of Construction Management at Deakin University, Joe worked full time on large scale residential and commercial projects within Melbourne. He also spent time in the UK, where he gained further valuable experience as a Contract Administrator with Higgins Construction on a large residential project.

We are very pleased to have you on board, Joe.