Steel is progressing quickly on the Coles Aurora box with the main roof members & purlins erected. Precast for the Coles Box is now 90% complete.
Footings for the Aldi store are progressing well and will be ready for precast in the coming weeks.
The Building C excavation & blinding had commenced & the site team expect to pour the slab after cup week.