It’s all happening at the Dan Murphy’s Pacific Epping Project!

Internally works continue to progress with the plaster and painting works to the trading floor and back of house areas well underway.

The cool rooms have been installed and the light fittings are being installed to the exposed cable tray.

Externally, our civil contractors have begun to prep for asphalt and pavements and kerbs are being installed to the car parking areas.