The team are progressing well at Highlands with the window framing installation nearing completion and glass ready to measure.

Stud wall framing has commenced with cladding preparation to the external frames beginning.

Civil works are progressing rapidly with the retaining wall footings nearing completion. This will then allow block work to commence soon after, along with the preparation of kerbs and channel.

Downpipes, box gutters and laying mesh to the upper and lower roofs progressed last week and the team are now ready to load the roof structure.

Brickwork to the facades have progressed and the retaining wall brickwork has begun.

Electrical & fire services rough-in is complete with the installation of the main switchboard expected to commence within the next fortnight.