The Highpoint team have successfully completed the removal of the first set of escalators.

An enormous effort was put in by all to drop the Centre Court set in one night.

Structural slab demolition has been completed to Node 5 and the Centre Court slab demolition is progressing well.

Structural steel erection for void re-profiling has commenced, and ceiling demolition to Zone 3 Level 2 is well under way.

Finishes have begun in Zone 3 Level 3.

The team have also successfully completed the removal of the decorative steel to the Zone 1 Level 3 Atrium Skylights.