The vinyl flooring and prep room tiling is progressing well inside the Woolworths box. Refrigeration cases are now complete allowing finishes trades to progress.

Precast and steel erection is now complete with works to the north façade progressing well. Glazing is nearing completion to external shop fronts with brick laying well under way.

Canopy finishes due to commence next week.

Thank you to all our subcontractors for their efforts in 2018 so far.

We’d like to wish everyone a safe and happy Easter. Enjoy the break!

Back