The Buxton team have reached a target milestone with a majority of the precast panels erected prior to the holiday break. This has enabled the steel rigging crew to continue their works from the heritage building to the ground steel beams under the New Art Gallery building.

The team is looking forward to progressing the new structure over the coming weeks.