The Coles Aurora team are continuing their strong momentum. Aldi has officially been handed over to the shopfitters and the team are now focusing on getting Coles ready for handover in the coming months.
The Coles box is beginning to resemble an open to the public supermarket. Tiling has begun on the walls of the preparation areas, the feature bulkheads in the preparation areas have been installed along with some of the feature display cases and refrigeration equipment, and a majority of the selling floor lighting has been hung.
The back of house Coles amenities areas is almost completely finished, with the vinyl flooring and the tiling complete. The mall entry to Coles is also almost complete, with sheeting to the facades and Liquorland well underway.
Building B precast and structural steel has been erected, the internal masonry walls have commenced erection and the roof is now being prepared to be laid. Building C & D framing for the metal cladding and glazing is underway.
The structural steel for the gym at the end of Building A has been erected bringing the final shape of the main building together. In-ground services are to go in before the slabs for the ground and first floor can be prepped in the coming week.
Last of all, the Coles Express shop floor slab is ready to be poured this week with precast and structural steel to follow early next week.
Great work Coles Aurora team!