After a well deserved break the team at Highpoint have had a good start to the year with the commencement of ceiling demolition to Zone 1 Level 3 in preparation for the new feature awning.

Decommissioning of the Zone 3 Travellators and Escalators has commenced, prior to two new sets of escalators being installed in the coming months.

Zone 3 Level 3 is nearing completion with the Big W Node ceiling demolition being complete, and ceiling finishes commencing.

Progress to Centre Court has seen painting of the feature awning in preparation for the timber batten installation.