During the past two weeks the Quest Pacific Epping team have been busy prepping for the level 2 concrete pours.
Pour 1 of level 2 is now complete, with pour 2 scheduled for tomorrow.
The level 3 precast cores have been installed and the first level 3 pour is set for after the Melbourne Cup Long Weekend
And the plumbers have been digging and installing in-grounds outside the job for incoming services for the hotel.