Over the past 2 weeks the team at Quest Pacific Epping have been working hard and fast!

The level 1 slab and stairs up to level 1 have been poured.

The stair master installation is now underway along with the framing for level 2 transfer slab.

Screens and precast cores from level 1 have been installed and the precast to the lift core is complete.

Great work team!